Commission Awards Moccasin Dam Pre-Construction Contract After Conflict Disclosure
Commission approved the CMGC contract for Myers Sukut Joint Venture, up to $85.1 million, authorizing only pre-construction services pending CEQA and DSOD review.
Why it matters: The project replaces a spillway whose capacity falls short of the updated design flood after the March 2018 event brought the reservoir within about 1.3 feet of the dam crest.