Cover image for Duke Holds Firm on Needmore Line as Commissioners Decry 'Greed'

Duke Holds Firm on Needmore Line as Commissioners Decry 'Greed'

Board of County Commissioners • Swain CountySeptember 1, 2026

Sources:

Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.

Archive locked

Duke Energy told Swain County commissioners Sept. 1 that its roughly 4-mile transmission route along Needmore Road is final, and that contact with property owners begins within weeks. In the same work session, the board heard a request to extend the county's data center moratorium by eight months, moved toward a $2.995M airport land purchase, and took up an order declaring the county finance officer's post vacant after a closed session.

  • Duke's Needmore Road route "set fully": landowner contact expected in 3–4 weeks as commissioners accuse the utility of "corporation greed"
  • Data center committee seeks 8-month moratorium extension to draft about 15 restrictive ordinances; vote expected Sept. 15
  • $2.995M airport property purchase heads toward state review, financed by settlement trust interest with a stated 0-cent tax impact
  • Finance officer post declared vacant in a motion after a closed session; interim designated, result not announced
  • Commissioner says sheriff's office travel charges topped the $6,000 figure given to the board

Why it matters: Families along Needmore Road will soon be asked for easements on their land. Because the line runs under 161 kV, it skips state Utilities Commission review, which leaves residents little formal leverage.

Get reports in your inbox

Follow this commission for free and get the next report delivered by email. You'll be able to access the full archive, get real-time updates, and track the topics or keywords you care about most.