Redwood City's council on Nov. 23, 2026, unanimously approved a project labor agreement covering five major capital projects worth an estimated $72 million to $86 million in hard costs. The Carpenters union asked for more time, but the rest of organized labor packed the hearing in support. Council also raised permit fees, approved its impact fee project lists and heard sustained opposition to any new license plate reader system.


  • Project labor agreement approved unanimously for five projects, including two storm drain pump stations, with a nonbinding 20% local-hire goal
  • Fee update adopted unanimously. Without it, the city would recover only 62% of service costs.
  • Parks and transportation impact fee lists approved as members flag a roughly $4.6M park debt still owed
  • At least eight speakers oppose new license plate readers. The mayor forms a review committee with a June 30, 2027, deadline.

Labor Deal Locks In Union Terms for Pump Stations

The basics: A project labor agreement, or PLA, is a pre-hire contract that sets wages, work rules and dispute procedures for a construction project before bidding begins. This one is between the city and the San Mateo County Building and Construction Trades Council.

Why it matters: The agreement covers five projects now in design, with construction slated for fall 2027 through spring 2028. They include the Price and Bradford storm drain pump stations and a downtown sewer pump station, which is core flood and sewer infrastructure.

Where things stand: Council made a PLA a priority in its FY2026-27 budget. Mayor Elmer Martínez Saballos formed an ad hoc committee in September with Councilmember Jeff Gee and Councilmember Chris Sturken, and it met three times. Union and non-union contractors can both bid. The agreement sets a goal of at least 20% of hours going to workers from Redwood City or North Fair Oaks, adds targeted-hire and apprenticeship provisions, bars strikes and lockouts, and excludes some work, such as small modular buildings. Any changes return to council.

"The intention of this policy is really to make sure that our city projects, our big construction projects, are being done in a timely way," said Mayor Martínez Saballos, who chaired the ad hoc committee.

Assistant City Manager Michelle Posh Flaherty said early data from peer agencies "suggests PLA projects may cost roughly 5 to 9% more than comparable projects." She described the estimate as preliminary.

Gee rejected that framing. "That low number is just the start number. It's not the end number and never is the end number," said Councilmember Gee. Vice Mayor Kaia Eakin also disputed that costs would rise. Councilmember Isabella Chu said the premium would be worth it either way: "Even if it really did cost 5 to 10% more, that's where I want my tax dollars going."

The other side: The North Coast States Regional Council of Carpenters did not oppose the agreement but asked council to postpone the vote. Staff said the city had engaged the Carpenters without resolving outstanding issues.

"The issue is the carpenters union only had six days to take a look at this, and that's just not enough time," said Matthew Miller, representative, Carpenters Local 217.

Councilmember Marcella Padilla pressed on enforcement: "Whenever I hear the word goal, I just—" Labor counsel John Holtzman said the 20% target is not binding. He said results depend on contractors and the supply of trade labor, and the city will receive a yearly report.

Decisions and stakeholder impacts: The resolution passed unanimously on a motion by the mayor. The Building Trades, the plumbers and pipefitters union (UA), sheet metal workers, painters and the San Mateo Labor Council all spoke in support, citing apprenticeships and local jobs.

"The PLA you have before you was forged in the fire of discourse and compromise," said Bart Pantoja, representative, San Mateo County Building and Construction Trades Council.

The Building Trades secured standardized terms on major public works. The Carpenters are left outside the deal for now, and Councilmember Diane Howard said she hoped they would reengage. Contractors and residents will judge the 20% goal by its annual reports, not its wording.

What's next: Construction begins in fall 2027 at the earliest. Annual reporting on local hours will follow.


Fees Rise to Close $142,000 Subsidy Gap

Why it matters: The city spends $376,913 a year on these services but collects about $234,000 under current fees. Without an update, roughly $142,000 a year would fall to the general fund.

Where things stand: The last citywide fee study was in 2023. Since then, a new street vending ordinance and new state laws have outdated the schedule. One state law, SB 22, caps heat pump water heater permits at $150 unless the city can justify a higher cost. Economic Development Manager Amanda Anthony said the existing schedule would recover just 62% of costs.

Consultant Government Consulting Partners calculated fully burdened hourly rates. The new schedule includes:

  • A building fee rising from $214 to $326
  • A $326 heat pump water heater permit, with a lower rate for swap-outs
  • New permits for motorized and non-motorized vendors
  • Restructured address-change fees and cannabis permit adjustments
  • A new cannabis business tax appeal fee
  • An identification permit for solicitors and peddlers, which Anthony described as "a badge that they're going to have to wear whenever they're soliciting or peddling."

Fees will rise each year with city salaries and benefits. A comprehensive study is planned for 2027-2028.

The other side: Gee noted building staff do not track their time and pressed on fee stacking. "I am not a fan of getting a permit and then starting and then saying, oh, by the way, you needed this permit and that permit," said Councilmember Gee.

Padilla asked how the city would reach vulnerable residents. Community Development Director Jeff Schwob said the city cannot subsidize fees without general fund money. "We can only charge the cost of providing service in the case of the fees that we're providing service for," said Schwob. He said education and incentives are the city's tools. Eakin and the mayor urged incentives for heat pump swaps and pointed to Peninsula Clean Energy rebates.

Decisions and stakeholder impacts: The resolution passed unanimously on a Howard/Eakin motion, with no public comment. Builders, street vendors, solicitors and cannabis businesses will pay more. Heat pump adopters pay more than the state's $150 baseline, though swap-outs get a lower rate.


Impact Fee Lists Pass as Park Debt Lingers

The basics: Under California's Mitigation Fee Act, cities must adopt an annual project list to justify the impact fees they charge developers. Redwood City's nexus studies, which link fees to projected needs, date to May 2022 for parks and January 2024 for transportation.

Where things stand: The number and type of projects did not change, though some transportation timelines shifted. Lucas Wilder, Assistant Director, Parks, Recreation and Community Services, outlined goals to acquire about 53 acres, keep parks within a 10-minute walk and renovate Hoover Park. He said fee deferrals allowed under SB 937 delay revenue.

Transportation Manager Malahat Orang said transportation fees mainly serve as the local match for grant-funded projects. Those include Jefferson Avenue, backed by a $4.5M grant, Bay Road, Page Street and the $398M 101/84 interchange.

The other side: Sturken called the gap between the $21.8M near-term list and expected revenue a narrow margin. "I want to just set the expectation that we have more to do in order to get there," said Councilmember Sturken.

Chu warned that fees can backfire. "If our park fees are so high that they are preventing development, then that ultimately means fewer affordable housing units, fewer parks, fewer homes," said Councilmember Chu.

Gee said "it's not the right fiduciary responsibility to spend funds before we collect them." City Manager Patrick Heisinger quantified the park program loan: "I think we've received about $400,000, so we have about $4.6 million left outstanding plus interest."

Padilla urged faster synthetic turf work at fields such as Taft. "I just want to advocate for getting our fields fixed a lot faster than 10 years," said Councilmember Padilla. Howard said the list gets projects "shovel level ready" for grants. Eakin said "the answer is not fund fewer parks."

Decisions and stakeholder impacts: Both resolutions passed unanimously on the mayor's motion, with no public comment. Approving the lists keeps the fees legally defensible. However, slow development and deferrals leave park projects, school-field upgrades and loan repayment exposed.


Residents Line Up Against License Plate Readers

Why it matters: The city's contract with Flock, an automated license plate reader (ALPR) vendor, has lapsed. Speakers want no replacement from Axon or anyone else. The next decision point is a committee recommendation due by June 30, 2027.

Where things stand: At least eight speakers opposed ALPRs during general public comment, several of them members of Safety Over Surveillance Redwood City.

"We're grateful that the city staff has wisely decided to hold off on bringing a recommendation on a new surveillance contract until 2027 after receiving additional community input," said Bill Newell, public commenter. Newell argued Axon fails end-user requirements under the California ALPR Privacy Act.

Other speakers raised these concerns:

  • Hannah Dorris cited hacking and use of camera data by other states to enforce laws such as abortion bans.
  • Liz Pang said switching vendors does not cure privacy concerns.
  • Clara Jekyll, speaking individually, cited a 2026 report from the state Racial and Identity Profiling Advisory Board on racial disparities.
  • Sarah Matlin cited a Rapid Response Network report of at least 57 San Mateo County residents detained by ICE in 45 days.
  • Judy Serebrin noted other Peninsula cities did not renew their contracts.
  • Karen Turner urged real-time-only use with rapid deletion if council proceeds, citing New Hampshire's law.

Decisions and stakeholder impacts: No action was taken during comment. Later in the meeting, the mayor formed a temporary ALPR review ad hoc committee with Padilla and Howard. It will advise staff on safeguards and best practices.

What's next: The committee sunsets once it delivers a recommendation to council, due no later than June 30, 2027.


  • Consent calendar: Approved unanimously, apart from Item 7E. It included Item 7F, a five-year Ace Parking agreement adding meter collection and maintenance. Ace backed the deal, while a commenter objected to broken meters and higher rates.
  • Item 7E: Passed with four votes after Chu, Gee and Sturken recused themselves over ties to a Stanford development.
  • King tide warning: Heisinger said tides could reach 9 feet or more over three to four days. About 5,000 sandbags have been filled, and crews are working around the clock.
  • Staff departure: Council honored Posh Flaherty, who is leaving to become Auburn's city manager.
  • Equity subcommittee: Recommended considering a land acknowledgment in early 2027 and highlighted a NovaWorks paid internship program for ages 18 to 24.

Council adjourned to a closed session on existing litigation, and the mayor said no reportable action was expected. The next meeting is the Dec. 7 council reorganization.