Council Freezes New Data Centers for 45 Days, Exempts Avayo Phase 1

City Council • PittsburgOctober 26, 2026

Sources:

Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.

Preview only

Pittsburg put a 45-day hold on new and expanded data centers Monday, but the project that drew a packed, angry room, Avayo's already-approved Phase 1, keeps moving. At an Oct. 26, 2026 special meeting, the City Council adopted an interim urgency ordinance 4-0, with Mayor Dionne Adams recused. The vote buys time, but residents say it doesn't buy them what they asked for.

  • 45-day citywide data center moratorium adopted 4-0, covering Avayo Phases 2 and 3
  • Avayo Phase 1 exempt; staff and the acting city attorney cite completed entitlements and environmental review
  • Residents demand 90 days, a Phase 1 halt and an outright ban; staff says 90 days isn't legal yet
  • Building trades oppose any moratorium, pushing labor standards instead
  • Mayor concedes the city "fell short" on communication; Councilmember Killings reads the public record back

The basics: California Government Code Section 65858 lets cities adopt temporary "urgency" zoning moratoriums while they study new rules. They take effect immediately but require a 4/5 council vote.