La Quinta Eyes Developer In-Lieu Fee to Fund Undergrounding Power Lines
City Council • La QuintaNovember 3, 2026
Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.
La Quinta has required buried utility lines since 1982, yet most of the Cove and village still sit under overhead wires, and the estimated cost to fix that is about $171M. At an Election Day study session on Nov. 3, 2026, the City Council took no vote but signaled support for studying a fee on new development and forming an ad hoc committee. The meeting's other themes were also about building: the Imperial Irrigation District (IID) described a regional power buildout of about $280M, and Silver Rock's owner set a summer 2027 construction target.
- Council favors studying an undergrounding in-lieu fee paid by new development, not existing owners
- IID outlines about 324 MVA of new capacity, about $280M, as transformer supply limits slow delivery
- Silver Rock owner targets summer 2027 for full-site construction after the last homes were demolished
- Ordinance 639 on dogs running at large introduced, declared unanimous, with an "enclosed" yard fix
Undergrounding: A Fee to Replace Waivers
The basics: Undergrounding moves overhead utility lines below ground. An in-lieu fee lets a developer pay into a city fund instead of doing the work on site.
Why it matters: City studies from 2009 and 2023 put undergrounding six areas at about $171M, including $147M for the Cove alone. A developer fee would start building a fund without assessing existing property owners.
Where things stand: The city's undergrounding requirement often gives way to waivers on infill projects, because moving a few poles can mean adding poles elsewhere, said Design and Development Director David Newell. Smaller study areas ranged from $3M to $5M.
Staff pointed to fee programs in Pismo Beach and Watsonville. One example Newell cited charges $300 per lineal foot. The package could include underground-ready conduit, waiver-of-protest conditions and credits against any future assessment district. Adopting a fee would require a nexus study, the analysis that ties a fee to the impacts of new development, plus code amendments. Staff explicitly did not propose assessment districts on existing owners.
The cost of the work is the problem. Guillermo Barraza, IID Power Department Deputy Manager, gave a rough estimate of $175 to $300 per foot. IID is a cost-of-service utility and does not offer the state Rule 20 credits that investor-owned utilities use to help communities fund undergrounding.
"If it costs us a dollar to put that infrastructure in, we charge you a dollar for it," said Cameron Butcher, IID outside counsel.
The legal path favors a fee. "Those would not need to be approved, but they would only apply to new development," said the City Attorney. Assessments or taxes, by contrast, would require a vote.
The other side: One councilmember worried about collecting money with no committed project. "My only concern with that is if we start charging people for fees, but we don't do anything, right?" the councilmember asked. City Manager Jon McMillen said the aim is a plan paired with a one-time fee.
Pat Healy, a Cove resident, asked why the city wants to do this, how it would work and what it would cost. He said he came because of an email from Kay Wolf. "I don't know that it seems like a great idea to do something that costs 3 times as much as if you'd done it right the first time," Healy said. Wolf generally supported undergrounding in a written comment. She asked for clear, factual information for voters and asked where the city stands on advocacy.
Decisions and stakeholder impacts: "But no decisions tonight since it is a study session," said Mayor Linda Evans. Councilmembers favored studying an in-lieu fee and forming an ad hoc committee. The committee would include business, resident and Planning Commission members, and possibly IID. Newell suggested adding a couple of members of the Finance Advisory Commission. Infill developers would pay instead of seeking waivers. Cove and village owners avoid assessments for now, but the funding gap remains large.
What's next: A community workshop was mentioned for February. A fee would need a nexus study and code amendments before adoption.
IID Maps a $280M Power Buildout
Why it matters: Electric capacity determines when Silver Rock, Highway 111 corridor projects, hotels and housing can move forward.
Where things stand: The capacity IID added in the early 2000s is running out, said Cameron Butcher, IID outside counsel. He said about 324 MVA of new capacity is under construction or in development. Projects include:
- Marshall substation
- North La Quinta substation
- A third transformer bank at Jefferson, which IID later tied to Silver Rock
- An Avenue 58 transformer expected in mid-2028
- New substations in Indio, Cook Street, Calhoun and Thermal Ranch
Equipment lead times have improved from about 3.5 years to 19 to 22 months, Butcher said. Costs remain high, and critical-infrastructure rules limit which suppliers IID can use.
"We expect to receive it by the end of the year, January at the latest," said Guillermo Barraza, IID Power Department Deputy Manager, of the Marshall transformer.
Decisions and stakeholder impacts: No action was taken. IID funds projects through joint powers agreements, cost-share agreements and surcharges. Only Indio has enacted a surcharge. A councilmember noted that La Quinta chose not to surcharge residents and instead allocated up to $10M. Developers will continue to depend on IID will-serve letters, which confirm that power is available, and on IID's customer service proposal process.
Silver Rock Clears Homes, Targets 2027
Where things stand: The last of 29 homes in Silver Rock's Dogbone area was demolished the morning of the meeting, said Michael Gazzano of Turnbridge Equities, which owns the site. Slabs remain and will be removed during final grading. The site development permit application is on track for the end of 2026, and the golf clubhouse will be relocated.
"We are kind of scheduled to be under construction on the full site summer of 2027," Gazzano said.
The other side: Mayor Evans raised erosion risk from an expected El Niño winter and the January golf tournament. Gazzano described plans to protect the temporary golf parking area and offered to brief the Chamber of Commerce.
What's next: Power remains a gating item, with IID tying Jefferson substation upgrades to the project. Council met in closed session on Silver Rock litigation and reported no action.
Dog Leash Ordinance Advances With Yard Fix
Where things stand: Ordinance 639 builds on the Riverside County animal control code, which the city adopted with amendments on April 21, 2026. It clarifies definitions and administrative restraint orders for potentially dangerous animals. It also adds Section 10.04.180, which requires dogs to be restrained in public and on private property, except in dog parks. "Leashes or tethers must be durable, no longer than 6 feet," said Lisa Chastain, Public Safety Management Analyst. Violations can be documented through observations, photos and video.
The other side: Councilmembers asked about fenced yards, dogs that run out to greet owners and invisible fences. The City Attorney said dogs on unenclosed property must be close to and under the effective control of their owners. Dogs in enclosed yards need no leash, and electronic fences alone are not enough.
Decisions and stakeholder impacts: Council changed "fenced" to "enclosed" and fixed a typo. Mayor Evans declared the introduction passed unanimously. Owners with enclosed yards keep their flexibility. Owners relying on invisible fences would need another form of restraint.
What's next: A second reading is required before adoption.
Minor Items
- Consent items 1 through 3 passed unanimously. Item 4, a demand register including SoCalGas, passed separately (For: 4, Against: 0, Abstain: 1, Councilmember Deborah McGarrey, citing an employer conflict).
- Coral Mountain trail: Resident Mary Mann said Coral Mountain Club fencing blocks a trail near 58th Avenue and Madison Street that has been used for more than 100 years. Staff will report back.
- Coachella Valley Mountains Conservancy: The Conservancy has invested more than $7M in 30 valley projects in 2025, none in La Quinta. It invited Prop 4 grant applications and noted a $1.2M CVLink shade award.
- Friends of the Desert Mountains reported 18 La Quinta events and 499 attendees in the past year. Its fundraiser is Nov. 18.
- Alerts: Residents must opt in to AlertLQ and other city channels before the expected El Niño winter and December's Ironman.
Looking Ahead
Ordinance 639 returns for a second reading. The undergrounding workshop is expected in February.