Nuclear Advocates at COP31: Licensing, Suppliers, Talent Stand Between Pledges and Plants

Nuclear Advocates at COP31: Licensing, Suppliers, Talent Stand Between Pledges and Plants

COP 31 Side Events • United NationsNovember 19, 2026

Sources:

Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.

At a COP31 side event on Nov. 19, 2026, nuclear industry leaders argued that the global pledge to triple nuclear capacity by 2050 will be won or lost on permit paperwork, supplier quality and workforce pipelines. A panel moderated by the Japan Atomic Industrial Forum took up most of the program. It followed a World Nuclear Association outlook showing that government goals now exceed the tripling mark, though 548 GW of that ambition is not yet tied to any project.


  • Almost two years of paperwork to request a 10-year license: an Ontario Power Generation panelist urges faster licensing without cutting safety
  • The cheapest bid isn't the safe bet: an Akkuyu procurement specialist says nuclear-grade suppliers are a different business
  • Japan eyes about 20% nuclear by 2040, up from 9.4% in 2024; Türkiye's Akkuyu plant is expected to cover about 10% of national demand
  • Government goals total 1,467 GW by 2050, above the 1,200 GW tripling target, but 548 GW has no assigned projects
  • Construction starts must rise sixfold within five to 10 years; there have been 14 starts in 2026 versus 11 in 2025
  • WNA issues 12 policy recommendations and rates the U.S. 400 GW target low on achievability

From Ambition to Action: The Bottleneck List

Why it matters: Panelists argued that political targets will not build plants without predictable licensing, qualified suppliers and a trained workforce. That is the unglamorous layer that turns COP pledges into steel and concrete.

Where things stand: licensing. Aditi, a regulatory affairs professional at Ontario Power Generation and COP31 co-lead for Nuclear for Climate, described relicensing OPG's Darlington and Pickering plants before Canada's nuclear regulator, the CNSC. "Just to ask them to give us a 10-year license, it took us almost two years to put the paperwork together," she said.

She said security, emergency management, environmental protection and Indigenous relations each add scrutiny and cost. She called for regulators to coordinate internationally and suggested AI could help streamline the process. She also insisted that easing the burden must not mean weakening oversight: "Safety is what makes innovation possible."

Where things stand: suppliers. Türker Göktaş, who works in procurement and supplier management for the Akkuyu Nuclear Power Plant project, drew a hard line between ordinary and nuclear-grade manufacturing. "Manufacturing a component and manufacturing a component that meets the nuclear standards are totally two different things," he said.

Göktaş cited ISO 19443 traceability requirements and warned that supplier delays or poor-quality choices can cost millions of dollars. "The cheapest quote is not always the one we should go with," he said.

Where things stand: people. Daniel Liu, a panelist from the Japan Atomic Industrial Forum, said Japan's long gap in construction has strained both skills and suppliers. He pointed to uncertainty about future projects, the challenge of passing knowledge to new workers and the need to support smaller suppliers. Japan's response is the Japan Atomic Human Resources Consortium (JARC), launched in October 2026, which plans a roadmap by the end of fiscal 2026. Liu said cooperation with Türkiye could cover quality assurance, supplier development and youth exchange.

Göktaş told young professionals not to wait. "We do not need to wait for a country's decision to build a nuclear power plant," he said. He argued that building a nuclear program means building a whole ecosystem, including non-nuclear disciplines and lawyers. He cited a localization roadmap for Rwanda and called for practical training and exchanges.

Decisions and stakeholder impacts: The panel took no formal action. Utilities facing relicensing, regulators weighing international coordination, and small suppliers seeking nuclear qualification were the clearest audiences for its message. Young engineers were cast as the deciding variable. Moderator Jun Arima, Board Member, Japan Atomic Industrial Forum, closed with three messages: nuclear should complement renewables, the industry needs practical solutions, and progress depends on international cooperation and young professionals. "We must move from ambition to action," Arima said.

What's next: JARC's roadmap is due by the end of fiscal 2026. Arima argued that concrete investment, cooperation and talent are needed by 2035.


Japan and Türkiye Make the National Case

Why it matters: Both countries frame nuclear as a way to meet rising electricity demand while improving energy security and building industrial capability.

Where things stand: Liu noted that "nuclear supplies only 9.4% of Japan's electricity in 2024." He described an outlook of about 20% by 2040, alongside 40% to 50% from renewables. He emphasized reactor restarts, replacement reactors and exports of Japanese equipment and expertise.

Göktaş said Akkuyu's four units would cover about 10% of Türkiye's electricity demand. He cited a Deloitte report estimating roughly a 3x return to GDP for every dollar invested. He also noted Türkiye's goal of about 10 GW of small modular reactors (SMRs) by 2050. SMRs are smaller, factory-oriented reactor designs.

For Canada, Aditi pointed to OPG's SMR construction at Darlington.

Decisions and stakeholder impacts: No commitments were made. The framing positions Japanese suppliers as exporters and Türkiye as both a buyer and an emerging regional hub for skills and supply chains.


WNA: Tripling Is Achievable, Delivery Is Not Assured

Why it matters: Governments' stated goals add up to more than the tripling target. Delivery, however, depends on decisions made in the next decade and a steep rise in construction.

Where things stand: A World Nuclear Association presenter, walking through the World Nuclear Outlook Report, said "there could be 1,467 gigawatts of nuclear capacity by 2050." That figure exceeds the 1,200 GW needed to meet the tripling target set by 39 governments.

The capacity pipeline breaks down this way:
- About 423 GW of currently operable capacity is expected to still run in 2050, many reactors beyond 60 years of age.
- About 508 GW is under construction or planned.
- 548 GW is not yet assigned to any project.

Nuclear generation reached a record 2,702 TWh in 2025, comparable to wind and solar, each at about 9% of world electricity. The global fleet's capacity factor, a measure of how much of the time plants run at full output, averages 83.7% and shows no decline with age.

The catch: There have been 14 reactor construction starts in 2026, up from 11 in 2025. The WNA said it needs "construction start rates to increase over the next 5 or 10 years to being 6 times the current level."

The readiness scorecard: The WNA grouped countries as pace-setters, expanders, restarters, newcomers and candidates. It scored each on policy framework, institutional readiness, project readiness and target achievability. The U.S. 400 GW target rated low on achievability because the country lacks a clear program, though the presenters said that could change. The central gap, they said, is "converting targets and institutions to become financed, licensed, and repeatable projects."

Decisions and stakeholder impacts: The WNA's 12 recommendations cover:
- durable policy
- investment
- regulatory efficiency and cooperation
- use of existing assets
- proven designs
- fuel supply
- reprocessing
- waste and decommissioning
- supply chains
- programs over one-off projects
- workforce
- public confidence

The emphasis on proven designs and multi-unit programs favors established vendors and countries with existing fleets.


Minor Items

  • Nuclear Europe said nuclear supplies 24% of EU electricity and projects fleet growth from 100 GW toward 150 GW by 2050.
  • The group cited three growth routes: lifetime extensions, new large reactors and SMRs arriving in the early 2030s.
  • Nuclear Europe pitched dispatchable baseload nuclear for cement, steel, chemicals and data centers, describing nuclear and renewables as partners.

Looking Ahead

Watch for Japan's JARC roadmap by the end of fiscal 2026. Also watch whether construction starts move toward the sixfold increase the WNA says tripling requires.