Coastside Water Board Funds $273,000 Study to Merge Two Aging Tanks
Board of Directors • Coastside County Water DistrictOctober 14, 2026
Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.
The Coastside County Water District board took its first concrete step toward replacing two aging storage tanks in the district's southern service area with one at its Oct. 13, 2026, meeting. Directors approved a $273,000 preliminary design contract that opens a roughly $17.4M, multi-year capital project. They also approved an $799,667 excavation truck and three years of legal rate increases, then went into closed session on appointing a new general manager.
$273,000 EKI design contract approved to study replacing the Alves and Miramontes tanks with one tank
$799,667 hydro-excavation truck purchase approved 5-0, which staff said will mean safer digging around crowded utility lines
General counsel rates to rise 3.5% a year from 2027 through 2029, approved 5-0
First quarter finishes $358,000 ahead on contributions to capital projects and reserves
The basics: Engineering firm EKI Environment & Water completed a potable water storage master plan that ranked two priority projects. In September, the board approved design of the first, the Highlands/Carter Hill tank replacement. This vote advances the second.
Get reports in your inbox
Follow this commission for free and get the next report delivered by email. You'll be able to access the full archive, get real-time updates, and track the topics or keywords you care about most.