Coastside Fire Hires $898,649 Overseer Before Station 44 Bids Open
Coastside Fire Protection District • Coastside Fire Protection DistrictOctober 28, 2026
Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.
The Coastside Fire Protection District board voted 5-0 on Oct. 28, 2026, to hire an outside construction manager for the Station 44 replacement. Bids open Nov. 3. The board also finalized a new development-funded special tax at 142 California Avenue, and directors warned that rising costs could erode the district's healthy cash position.
- Swinerton wins $898,649 contract, 5-0, to oversee Station 44 construction and inspections
- Station 44 bids open Nov. 3 after six addenda and more than 250 clarifications
- Finance report shows a flat $17.2M revenue budget, but directors flag construction and fuel cost escalation
- CFD No. 40 special tax adopted 5-0 for development at 142 California Avenue
Why it matters: Station 44 is the district's largest capital project. The board is paying for independent oversight before bid prices land, a direct response to problems it experienced building Station 41.