Coachella Planners Give Highway 111 Storage Project One More Year
Planning Commission • CoachellaNovember 4, 2026
Locunity is an independent informational service and is not an official government page for this commission. All information is sourced from public footage and an analysis of official agendas with the aid of responsible, fact-checked AI. to report an error or omission.
Power shortages and soft market conditions have kept a planned RV and self-storage expansion on Highway 111 from breaking ground for nearly three years. On Nov. 4, 2026, Coachella's Planning Commission voted 3-0 to extend the project's permits a second time. Staff also put the applicant on notice that only one more extension remains before the project would have to start over.
- Sunridge Self Storage wins second one-year extension, 3-0, with two commissioners absent
- Electrical capacity and power costs remain the main barrier to construction
- One extension left: After that, the applicant must file a new application
Sunridge Expansion Buys Another Year
The basics: A conditional use permit (CUP) allows a use that a zone does not permit by right, subject to conditions. Here, it is paired with an architectural review approval (AR). The permits cover a roughly 63,000-square-foot self-storage building and 71 RV spaces on a vacant 4.86-acre parcel. The parcel sits next to the existing Sunridge Self Storage at 53301 Grapefruit Boulevard (Highway 111). The site is zoned manufacturing service and carries an industrial general plan designation.
Why it matters: The vote keeps 2023 entitlements alive on a commercial stretch of Highway 111 without new environmental review. The project still has no clear path to construction.
Where things stand: The commission first approved CUP 369 and AR 23-06 on Nov. 15, 2023, and adopted a mitigated negative declaration (Environmental Assessment 23-05). It granted a first 12-month extension on Oct. 15, 2025, with an expiration date of Nov. 15, 2026.
Staff recommended a second 12-month extension under Resolution PC-2026-34. The project would not change. Staff said no further California Environmental Quality Act (CEQA) review is required under Public Resources Code 21166, the section that limits additional review when a project and its circumstances have not materially changed.
Planning Technician Vanessa Sanchez-Mesa presented the staff report. She tied the delay to the "continued lack of available electrical capacity within the City of Coachella, unfavorable market conditions."
David Turner of Coachella Valley Engineers represented the applicant and said work is moving. He cited an upcoming meeting with the water district about removing an irrigation line that runs under the planned building. He also acknowledged that IID and other issues remain challenges. He was the only speaker during the hearing, and no one spoke in opposition.
Decisions and stakeholder impacts: Commissioner Vanessa Ordórica moved to follow the staff recommendation, and Commissioner Oscar Fonseca seconded.
- Vote: For: 3 (Alyssa Torres, Oscar Fonseca, Vanessa Ordórica); Against: 0; Absent: 2 (Eva Lara, Isela Murillo). Alternate Commissioner Ambriz was also absent.
- Applicant: Sunridge keeps its approved plans and avoids restarting the entitlement process for now.
- The city: An industrial-zoned parcel remains vacant for at least another year, and its build-out depends on power availability.
The Power Problem and a Ticking Clock
Why it matters: Electricity, not zoning, is the real gatekeeper here. Commissioners pressed for signs that another year would make a difference.
Where things stand: Commissioner Fonseca asked the applicant directly: "what's going to be different?" He also asked whether extensions are capped.
Turner said construction pricing had stalled the project. "The prices were through the roof and it just didn't pencil," said Turner. He added that power costs from IID have climbed, though he believed the issue could be resolved. "The price for the power went up exponentially," Turner said.
Staff answered Fonseca's question about a cap. "So this would be the approval of the second 1-year time extension. There is one more that they could potentially apply for," said a city staff member. After that, the applicant would need a new application that restarts the process.
The other side: Commissioner Torres asked whether the electrical situation could be fixed within the one-year extension. Turner said he thought so but described costs as a moving target. That hedge leaves real doubt about whether the project will build before its options run out.
What's next: The applicant may seek one final one-year extension. If power capacity and costs remain unresolved after that, the project would need a new application.
Minor Items
- Agenda and minutes: The commission approved the agenda and the Oct. 21, 2026, minutes, 3-0 each, with Lara and Murillo absent.
- Staff farewell: Vanessa Sanchez-Mesa, a planning technician who started with the city as an intern, attended her last meeting. She is leaving to become an assistant planner in Cathedral City. "I got another person in another city that I can go and bother once in a while," joked Commissioner Fonseca.
Looking Ahead
Watch whether Sunridge returns for its final extension, and whether IID power capacity along Highway 111 improves enough to move industrial projects forward.